Thursday 14 May 2015

Museum Halt Ballasting - Final Day

Today we completed ballasting at Museum Halt, which has been a real team effort. We think it looks fabulous and makes the platform area look much better than before!








Wednesday 13 May 2015

Gala Weekend!


Museum Halt Ballasting - Day 4

Further work has been completed at our Museum Halt platform regarding ballasting. A few pictures are below.




 As the track stood this morning:


Arrival of the Ballast:





 The completed product of the days work:




One final day is required to complete the new siding's ballast and then our next project can begin.

Thursday 7 May 2015

Museum Halt Ballasting - Day 3

During the process of getting the flat wagons, we need an area to store them when not in use. We currently store them within the Loop, however, to ease the use of the main sets of carriages during running hours, after some planning we are currently creating a storage siding to store them in.

Over the past two days we have started on the ballasting and creating of the siding for them.



Three of the completed track ballasting.






Stages of creating a ballast base for the new siding.


Finally the start of the siding. The first three sleepers and track layed down.

We need to complete the ballasting next week, then create a set of removable points. Keep an eye out for how we plan to construct them!


Wednesday 29 April 2015

Museum Halt Ballasting - Day 2

Today we have been out and about again ballasting. The pictures below show some of the work we have been doing.



Before Starting Ballasting


After Ballasting


The Completed Section

Some Training Shots:






Overall a successful two days. Now we just need to create a new siding to store the Wagons in, along side the Gantry.



Tuesday 28 April 2015

Flat Wagon Update 28/4

So, we finally completed the work in creating a ballast wagon from the flats today.



 Preparing the Flats for the days work.


Loading up the wagons!


Filling up the first load into the wagon.




Rio-Gen sits at Lakeside awaiting the digger to be loaded back up for the return journey.

Wednesday 22 April 2015

Flat Wagon Progress Report 22/4

So today we finalised plans for our flat wagons, and prepared one of the wagons for sides to go on tomorrow. We shall be around from around 10:00 tomorrow if you want to see the progress in person.






Catch the video here:
https://www.facebook.com/153361121356847/videos/vb.153361121356847/1154747897884826/?type=2&theater

The three flat wagons have identification plates as: 

NGF 4015, 4022 and 4044. Still to get names.